The Problem
A Midwest power generation plant had an active leak on its Unit 2 absorber discharge pipe. The leak was at a flange and the end of the pipe, where the line forms a four-way tee directly over a sump. The tee sits on a stand with a welded bracket underneath. The line normally operates at 38 psi and can see pressures up to 125 psi. Plant crews had already wrapped the pipe to try to stop the leak before RAK arrived.
The Solution
RAK prepared the flange and pipe end and stopped the active leak. At the plant’s request, the crew then encased the full flange together with the bracket underneath it. The encased section was reinforced and finished with a protective top coat. The leak was completely stopped, and the crew completed the work in a single day on site.